Fay Al Reeman II
Al Shamkha, Абу-Даби · Aldar Properties
Project factsheet
Photos and renders of the community and grounds — not of this particular home.
About the community
A villa community in Al Shamkha, Абу-Даби, currently under construction. Developer — Aldar Properties.
Specifications for Fay Al Reeman II as published by the developer — the project is under construction, so there is no Land Department record yet. They describe the whole community, not the individual house.
About the project
Fay Al Reeman II is a villa community in Al Shamkha, Абу-Даби.
The developer is Aldar Properties.
No lots from this project are in our database today. It is topped up every night, so listings for the building can turn up on any day.
Villas by Aldar in Al Shamkha: 557 homes with four to six bedrooms, 372 to 495 square metres, starting from AED 3.5 million, handover announced for Q4 2026.
What's announced
Fay Al Reeman II is the second phase of a villa community in Al Shamkha, Abu Dhabi. Per the developer's fact sheet: 557 units, villas with four to six bedrooms, sizes from 372 to 495 square metres, prices from AED 3.5 million. Sales launched in February 2023, with keys announced for Q4 2026.
Within the community, per the same document: a mosque, a school, retail, playgrounds, open green spaces, multi-purpose sports courts, and a pedestrian and cycling network. Estidama Pearl 2 rating, water-efficient fittings, sustainable materials.
Separately announced: a choice of exterior styles, a set of interior finish options, premium upgrade packages, and the ability to customise the house. That's unusual for a project of this scale, and it's the main thing worth confirming at the deal — what's included in the base spec versus the upgrade.
Four payment plans and milestone dates
On a separate payment sheet the developer offers four options: 40/60, 50/50 with a 2% discount, 60/40 with a 3% discount, and 100% up front with a 5% discount.
Under the 40/60 plan the breakdown is: 5% on signing the contract, 5% at the start of infrastructure works (31 August 2023), 10% on completion of piling (30 April 2024), 5% when the villa frames are half complete (30 November 2024), 10% when the frames are fully complete (30 June 2025), 5% on substantial completion of facades (28 February 2026), and 60% at handover (31 October 2026).
What matters here isn't the percentages but the milestones themselves: each carries a date, and together they show where construction was supposed to be in a given month. It's a ready-made checklist for asking whether the project is on schedule.
Unit type and count, sizes, starting price, community composition, rating and status — the developer's project fact sheet. The four payment plans and milestone dates — a separate payment sheet from the same developer.
The stock refreshes every night, and lots here appear and go. Message me — I will check the closed bases and suggest the nearest alternatives in Al Shamkha, Абу-Даби.
Ask about this projectFrequently asked about Fay Al Reeman II
Who is the developer of Fay Al Reeman II?
Aldar Properties.
How much does a house in Fay Al Reeman II cost?
No open lots for the building today. I will check the price of the layout you are after in the closed databases and send it with every cost of the deal worked out.
Where this project stands today
I will send the available layouts, the real entry price and what owners and tenants actually say about the building — without the brochure language.
Ask a question
Telegram is the fastest way — I answer personally.
Message on Telegram